悬挑式钢管脚手架施工方案
悬挑式钢管脚手架 第一篇

建设项目—XXXXX安置区工程

悬挑式钢管脚手架施工方案

编制:

审核:

目录

第一章、工程概况„„„„„„„„„„„„„„„„„„„„„4 第二章、编制依据„„„„„„„„„„„„„„„„„„„„„4 第三章、材料及要求„„„„„„„„„„„„„„„„„„„„4 第四章、外脚手架构造 „„„„„„„„„„„„„„„„„„„5 第五章、脚手架的搭设 „„„„„„„„„„„„„„„„„„8 第六章、脚手架的拆除„„„„„„„„„„„„„„„„„„10 第七章、安全措施及要求„„„„„„„„„„„„„„„„„„11 第八章、脚手架的设计计算„„„„„„„„„„„„„„„„„11【悬挑式钢管脚手架】

第一章 工程概况

本工程位于惠水县,为惠水县 XX。1#、2#、3#、8#楼建筑地上层数19层,地下室1层,4#~7#楼建筑地上层数6层,地下室1层,9 #~13#楼建筑地上层数7层。建筑面积约65933.6㎡, 1#、2#楼建筑物总高度64.2M,3#、8#楼建筑物总高度63.95M,4#~7#楼建筑物总高度,22.00M,9#~13#楼建筑物总高度21.60M.1#~8#楼建地下室为地下车库,一至三层为社区用房及商业用房,其余为住宅;9#~13#楼一层为商业用房,其余为住宅。 本工程外脚手架搭设拟采用悬挑式钢管脚手架,同时采用钢丝绳卸荷。脚手架沿高度方向采用一次沿四周满搭设的方式,搭设高度至塔楼檐口再加上1.5m。从七层面开始进行外挑架搭设,每六层一挑。每施工段塔楼搭设高度为18米,卸荷位置分别为:分别在第七层、十三楼面卸荷一次。

第二章 编制依据

1、《JGJ130-2001—建筑施工扣件式钢管脚手架安全规范 》 2、施工图纸

第三章 材料及要求

1、钢管

钢管采用外径为48mm,壁厚3.5mm,其材质应采用国家现行标准的要求。弯曲变形,锈蚀钢管不得使用。脚手架钢管每根最大质量不应大于25kg(6m长)。钢管上严禁打孔。 2、扣件【悬挑式钢管脚手架】

扣件包括直角扣件、旋转扣件、对接扣件及其附件、T型螺栓、螺母、垫圈等。脚手架采用的扣件,在螺栓拧紧扭力矩达65N·m时,不得发生破坏。 3、钢丝绳

钢丝绳选用6×19φ14.0光面钢丝绳,断股、锈蚀严重的钢丝绳不得使用。

4、脚手板

脚手板采用毛竹脚手板。 5、安全网

【悬挑式钢管脚手架】

安全网采用密目式安全网。

第四章 外脚手架构造

1、平面布置:附图1

立杆纵向间距1500mm,横向间距1200mm、900mm(用于A座有阳台立面),内排立杆距离建筑物的距离为300mm。立杆与大横杆必须采用直角扣件扣紧,不得隔步设置和遗漏。且立杆的直接头应相互错开500mm长,其接头距离纵向水平杆的距离不大于步距的1/3。 2、立面布置:附图2

【悬挑式钢管脚手架】

纵向水平杆步距1800mm,上下横杆的接长位置错开布置,错开距离不小于纵距的1/3,扶手杆水平设置于每步架0.9m高处。剪刀撑要求满设,并沿高连续布置,斜杆与立杆接触部位均用旋转扣件扣紧,其与水平杆的夹角为55°,剪刀撑的节点应在同一水平和垂直线上,其接长必须采用搭接,搭接长度不小于1000mm,用三个旋转扣件,除在两头与立杆和大横杆连接外,中间还增加2~4个节点。立杆和大横杆交点处一定设小横杆。 3、纵向水平杆的构造

根相邻纵向水平杆的接头不宜设置在同步或同跨内,不同步或不同跨两个相邻接头在水平方向错开的距离不应小于500mm,各接头中心至最近主节点的距离不宜大于纵距的1/3。 4、横向水平杆的构造

主节点处必须设置一根横向水平杆,用直角扣件扣接且严禁拆除。主节点处两个直角扣件的中心距不应大于150mm。在双排脚手架中,靠墙一端的外伸长度为150mm。 作业层上非主节点处的横向水平杆,宜根据支承脚手板的需要等间距设置,最大间距不应大于纵距的750mm。 5、立杆的构造

⑴.悬挑立杆必须放在悬挑型钢上的短钢筋上.

⑵.脚手架必须设置纵横向扫地杆。纵向扫地杆应采用直角扣件固定在距底座上皮不大于200mm处的立杆上。横向扫地杆亦应采用直角扣件固定在紧靠纵向扫地杆下方的立杆上。

⑶.立杆必须用连墙杆与建筑物可靠连接。

⑷.立杆除顶层顶步可采用搭接外,其余各层各步接头必须采用对接扣件连接。对接应符合下列规定:

①.立杆上的对接扣件应交错布置,两根相邻立杆的接头不应设置在同步内,同步内隔一根立杆的两个相隔接头在高度方向错开的距离不宜小于500mm;各接头中心至主节点的距离不宜大于步矩的1/3。

②.搭接长度不应小于1m,应采用不少于3个旋转扣件固定,端部扣件盖板的边缘至杆端距离不应小于100mm。 6、连墙杆

为了增强脚手架的侧向刚度及稳定性,在外脚手架于建筑物之间设置连接杆。 ⑴.连墙杆用短钢管制成,长度约500~800mm,一端用扣件固定于脚手架的立杆上,另一端与预埋在建筑物中的钢管相连。连接杆每层设置一次,水平间距4.5m,上下错开,成菱形布置。

⑵.连接杆尽可能设置在立杆与大、小横杆的连接处,与脚手架架体垂直,如在规定的位置上设置有困难,应在邻近点补足。 7、节点构造(见附图) 1)、工字钢悬挑构造

钢管悬挑脚手架方案
悬挑式钢管脚手架 第二篇

目 录

一.编制依据 ............................................................. 4

1.国家、行业和地方标准、规范、规程 .................................... 4 2.相关设计图纸 ........................................................ 4 3.安全管理法规文件 .................................................... 4 4.其他 ................................................................ 4 二.工程概况 ............................................................. 5 三.施工部署 ............................................................. 6

1.施工图及节点做法图 .................................................. 6 2.脚手架工程施工的重点、难点、特点 .................................... 6 3.脚手架体系选择与设计 ................................................ 6 四.钢管式悬挑脚手架搭设施工方案 ........................................ 10

1.搭设工艺流程 ....................................................... 10 2.脚手架搭设要求与措施 ............................................... 10 3.脚手架使用要求与措施 ............................................... 15 4.脚手架拆除要求与措施 ............................................... 16 5.质量标准及验收 ..................................................... 16 五.安全管理措施 ........................................................ 20

1.一般要求 ........................................................... 20 2.悬挑式脚手架的安全措施 ............................................. 20 六.文明施工要求管理措施 ................................................ 23 七.季节性施工安全技术措施 .............................................. 24 八.施工过程中的监测监控及维护保养措施 .................................. 25 九.应急预案 ............................................................ 26

1.重点防范部位的概况 ................................................. 26【悬挑式钢管脚手架】

2.防止脚手架安全事故发生的措施 ....................................... 27 3.应急施救措施 ....................................................... 28 十.环保措施 ............................................................ 29

一.编制依据

1.国家、行业和地方标准、规范、规程

1)《建筑施工扣件式钢管脚手架安全技术规范》(JGJ130-2001) 2)《建筑施工安全检查标准》(JGJ59-99)

3)《建筑施工高处作业安全技术规范》(JGJ80-91) 4)《建筑结构荷载规范》(GB50009-2001)

5)《北京市建筑工程施工安全操作规程》(DBJ01-62-2002)

6)《建设工程施工现场安全防护、场容卫生、环境保护及保卫消防标准》(DBJ01-62-2002)

7)《密目式安全网》(GB16909-1997)

8)《钢管脚手架、模板支架安全选用技术规程》(DB11/T583-2008) 2.相关设计图纸

中国气象局集体宿舍楼建筑施工图纸 中国气象局集体宿舍楼结构施工图纸 3.安全管理法规文件

1)《建设工程安全生产管理条例》(国务院第393号令)

2)《危险性较大的分部分项工程安全管理办法》(建质[2009]87号)

3)《北京市实施<危险性较大的分部分项工程安全管理办法>规定》(京建质[2009]841号) 4.其他

澳华城市花园12#-14#楼工程总承包施工合同 澳华城市花园12#-14#楼工程施工组织设计

二.工程概况

中国气象局集体宿舍楼工程位于北京市海淀区中关村南大街46号中国气象局院内。建筑面积16930.5m2,地上13层局部10层,结构形式为框架结构。

首层高首层为3.9米,其它层为2.8米,顶层层高为4.8米,建筑物檐口高度为38.6米。

根据现场条件和工期要求,涉及地下防水和肥槽回填,原来由肥槽搭设的架体需要拆除,所以地上整体结构施工时,不具备搭设落地脚手架的要求。本工程3-8层结构施工时脚手架体计划一次搭设三层,分别在二层、五层顶板上挑出,悬挑高度不超过8米。

三.施工部署

1.施工图及节点做法图

三层、六结构平法施工图;钢管悬挑架布臵平面图;脚手架搭设平面图。 2.脚手架工程施工的重点、难点、特点

本工程工期紧张,脚手架施工是保证工期的主要因素,尽可能的优化脚手架施工方案是工期顺利实现的前提和保障。

本工程外立面悬挑结构多,采用了南北两侧均分布有悬挑板,因此脚手架的悬挑形式将会单双排交替出现,给脚手架的设计、计算和搭设带来较大的困难。 3.脚手架体系选择与设计

本工程于2010年4月分开始地下结构施工,并计划于11月下旬结构封顶,工期十分紧张;但是主体施工至±0.00以上时,涉及地下防水及肥槽回填等工序,地下部分落

无悬挑板处钢管悬挑脚手架剖面图

有悬挑板处钢管悬挑脚手架剖面图

相关热词搜索:悬挑式脚手架图片 悬挑式脚手架规范

最新推荐成考报名

更多
1、“悬挑式钢管脚手架”由中国招生考试网网友提供,版权所有,转载请注明出处。
2、欢迎参与中国招生考试网投稿,获积分奖励,兑换精美礼品。
3、"悬挑式钢管脚手架" 地址:http://www.chinazhaokao.com/wendang/cehua/605146.html,复制分享给你身边的朋友!
4、文章来源互联网,如有侵权,请及时联系我们,我们将在24小时内处理!